Tomorrow, several valves along the Bonanza main line will be partially, or completely closed, in order to determine which valves will need to be shut down for the tie-ins to the new mains that have been constructed in the Bonanza area of the District as part of the Phase 2 Capital Improvements Project. Short Water Service Interruptions and Pressure Fluctuations (anticipated to be approximately a half hour in duration) will occur for Patrons serviced by these mains in the Bonanza area as well as Grouse Meadows during this testing tomorrow, Friday, June 13, 2025.
The actual tie-ins are planned for the week of June 23rd, and will necessitate a total shut down of the water system for all Patrons.
Please monitor the blog over the next week for additional and specific information as the schedule is finalized.
Reminder: Patrons who have had their water service interrupted, should open one inside tap slowly to vent any air that may have gotten into their plumbing, and then flush their lines until running water is clear during first use.