Wednesday, October 10, 2018

Update

We are a little bit behind schedule on the BORLEY project, it looks like it’s gonna be closer to six or 630 before the water is turned back on

Committee meeting

"Committee meeting, Friday, October  12th 10:00, at  7739 E. Sunnyside road for number crunching on water use rates for next fiscal year. This is a non voting meeting"  

Tuesday, October 9, 2018

Borley news

We will be doing the switch over to the new replacement pipe on upper Borley Road tomorrow. Please have some extra water on hand as I will be shutting the water off about 10 AM. We will be doing the switchover, line flushig and sanitizing and then we will re-flush the line again. I hope to have all water service restored to normal by 5 PM tomorrow. Mike.

Borley update

The line replacement on Borley road continues, we plan on tieing in to the new line today. At this time I do not know what time that will be. Water will be off for several hours. I am asking all patrons to stay away from the job site. It is not safe to have people walking around and it distracts the crews and delays progress. Thanks Mike.

Monday, October 8, 2018

Borley update

The Borley project continues, most of the pipe is in and tie in to the new pipe will probably be today or tomorrow. Please have some extra water on hand , because when we tie in, the line needs to be sanitized and then flushed. Please check the blog regularly, Mike.

Thursday, October 4, 2018

Borley update

They work on upper Borley Y Rd. continues the leak has become much worse so I have turn down the water volume trying to keep everyone in water service but you will notice definite reduction in pressure and volume. This is only temporary until we can switch to the new line that is being placed. Thanks Mike

Wednesday, October 3, 2018

Borley

We are currently working another repair on Borley road we anticipate the water being back on by 6 PM tonight. Mike