Wednesday, February 2, 2022

Status Update: 6:00 PM

After getting the parts to mount the new 40 HP pump today, Wednesday, February 2nd, work commenced this afternoon.  Unfortunately, towards the end of the job, it was discovered that there was an incompatibility between the coupler on the motor and pump stack shaft, so the installation had to be halted.  Parts are now being sought to remedy this incompatibility so that the install can be completed.  We do not at this time have a new schedule for completed pump installation.

The reservoir was standing around two feet this evening, down from about two and half feet this morning. 

We must ask you to please continue to minimize all water use immediately until further notice.

 

Check the District blog at www.kcwd1.blogspot.com for more information and further updates.

If you have not already done so, please sign up for email subscription updates from the blog by clicking on the “Subscribe” button on the homepage.

Thank you.