Status Update: Thursday, 4:45 PM

Last night a Patron of the District was able to machine a part to get the motor coupled with the pump stack.  Work crew has been working all day trying to troubleshoot in order to get the pump working.  They have not been successful yet, and work is continuing.


The reservoir is at 1.7 feet.


Please minimize water use!  We are doing everything we possibly can do to get the system back online.

Wednesday, February 2, 2022

Status Update: 6:00 PM

After getting the parts to mount the new 40 HP pump today, Wednesday, February 2nd, work commenced this afternoon.  Unfortunately, towards the end of the job, it was discovered that there was an incompatibility between the coupler on the motor and pump stack shaft, so the installation had to be halted.  Parts are now being sought to remedy this incompatibility so that the install can be completed.  We do not at this time have a new schedule for completed pump installation.

The reservoir was standing around two feet this evening, down from about two and half feet this morning. 

We must ask you to please continue to minimize all water use immediately until further notice.

 

Check the District blog at www.kcwd1.blogspot.com for more information and further updates.

If you have not already done so, please sign up for email subscription updates from the blog by clicking on the “Subscribe” button on the homepage.

Thank you.

Status Update: 2:00 PM

Parts received.  All trades on site installing 40 HP pump.  Will post updates when received from work crew.



Status Update: 8:00 AM Wednesday

Reservoir is at 2.5 feet (for reference:  full reservoir is ~13-14 feet)

Standing by at plant awaiting call from service provider that they are on the way with the parts that were shipped overnight.

Please do everything you can to minimize your water use for today until we can get the 40 HP pump installed.

Tuesday, February 1, 2022

Update 8:30 PM Tuesday Evening

 To All Patrons:

The reservoir level has dropped to two (2) feet as of this evening.  

Please do everything you can to minimize your water use for another day until we can get the 40 HP pump installed.



Update 3:00 PM Tuesday: Pump Installation Delayed One Day

Service Provider located the necessary parts and is having them shipped overnight.  Scheduled to be on site tomorrow to install the new 40 HP pump.  Installation will most likely take the full day, so not anticipating having the pump back on line until late Wednesday.

Please continue to minimize water use until District notification of full system recovery mode.

Continue to Minimize Water Use!

The reservoir had dropped back down to three feet this morning, so please minimize water use so that we can do a repeat of yesterday!

Our service provider had some bad news this morning, as they were unable to get some of the critical parts from their sources as expected.  They believe they have located the right parts in the Tri-Cities area and are pursuing getting those picked up. Work to install the new pump that was planned to start this morning is delayed.

Please make every effort to minimize water use until further notice.


Check the blog for further updates.