There was a large draw down through the night and early morning leaving the reservoir at around five (5) feet this morning from our reported 11.5 feet last night.
A reminder:
DETOURS ON WEDNESDAY, JULY 14TH:
The current plan is to begin repair work very early in the morning on Wednesday. Mullan Trail Rd. will be closed at Sunnyside at about 5:30 AM on Wednesday, so please use Sunnyside to Lake Shore to Sherman to access Hwy 90. If you are going east on Mullan Trail Rd. to get to Sunnyside, please detour through Tumble Creek Rd. to Shiras to get around the closure on lower Mullan Trail Rd. The repair is estimated to take most of the day and into the evening, and final restoration work on the road may happen over a few days.