Monday, August 9, 2021

Partial District Power Outage - Vista Booster Pump Station Down

10:30 AM:  Power has been restored, and all booster pump stations are operating.

7:45 AM:  Avista crew estimating that it will take at least two hours to replace the pole, so original estimate of 8:15 AM will not be met.  Expect no later than noon.  Also, power outage includes Grouse Meadow booster pumps, so all Patrons served by those pumps are also experiencing water service interruptions.

7:25 AM:  Avista crew has arrived onsite at broken pole.


A transformer blew near the Bonnell substation around 12:30 AM, and power is still out for those Patrons on that grid, including the Vista Booster Pump Station.  All Patrons serviced by that pump station are experiencing water service interruptions (e.g. Vista Loop, Highview Dr.).  Avista website reporting an 8:15 AM ETR for power, which will bring those pumps back online.